Section AB101 General

AB101.1 Permit fee schedule.

Permit fees shall be in accordance with Table AB101.1.

TABLE AB101.1 PERMIT FEE SCHEDULE

TOTAL VALUATION

FEE

$1 to $500

$24

$501 to $2,000

$24 for the first $500; plus $3 for each additional $100 or fraction thereof, up to and including $2,000

$2,001 to $40,000

$69 for the first $2,000; plus $11 for each additional $1,000 or fraction thereof, up to and including $40,000

$40,001 to $100,000

$487 for the first $40,000; plus $9 for each additional $1,000 or fraction thereof, up to and including $100,000

$100,000 to $500,000

$1,027 for the first $100,000; plus $7 for each additional $1,000 or fraction thereof, up to and including $500,000

$500,001 to $1,000,000

$3,827 for the first $500,000; plus $5 for each additional $1,000 or fraction thereof, up to and including $1,000,000

$1,000,001 to $5,000,000

$6,327 for the first $1,000,000; plus $3 for each additional $1,000 or fraction thereof, up to and including $5,000,000

$5,000,001 and over

$18,327 for the first $5,000,000; plus $1 for each additional $1,000 or fraction thereof

Source and transcript record

Record Georgia · 2024 IRC · Appendix AB Permit Fees

Effective January 1, 2026 · source captured Aug 30, 2026

Transcript SHA-256 5e789d690818642b4924351c2be2d7646ed1f51aad98657c3e4a9c1a345b0596 · text SHA-256 d2a6f2b89fd0f8f580ae0a17ec3e0abacb1cb847a201322b0b494cd42122116b

Adoption authority · Official amendments · ICC chapter source