APPENDIX AW
3D-PRINTED BUILDING CONSTRUCTION
SECTION AW101
GENERAL
AW101.1 Scope.
Buildings, structures and building elements fabricated in whole or in part using 3D-printed construction techniques shall be designed, constructed and inspected in accordance with the provisions contained in this appendix and other applicable requirements in this code.
SECTION AW102
DEFINITIONS
3D-PRINTED BUILDING CONSTRUCTION. A process for fabricating buildings, structures and building elements from 3D model data using automated equipment that deposits construction material in a layer-upon-layer fashion.
ADDITIVE MANUFACTURING MATERIALS. Materials used by the 3D printer to produce the building structure or system components of the building.
FABRICATION PROCESS. Preparation of the job site and construction material, the deposition, curing, finishing, insertion of components and other methods used to construct building elements such as walls, partitions, roof assemblies and structural components, and the means used to connect assemblies together.
PRODUCTION EQUIPMENT. The equipment, including the 3D printer, its settings, nozzles and other accessories used in the fabrication process.
SYSTEM COMPONENTS. Devices, equipment and appliances that are installed in the building elements as part of the wiring, plumbing, HVAC and other systems. These include, but are not limited to, electrical outlet boxes, conduit, wiring, piping, tubing and HVAC ducts, each of which is covered by a product standard or installation code requirement.
SECTION AW103
BUILDING DESIGN
AW103.1 Design organization.
3D-printed buildings, structures and building elements shall be designed by an organization certified in accordance with UL 3401 by an approved agency and approved by the building official in accordance with this section.
SECTION AW104
BUILDING CONSTRUCTION
AW104.1 Construction.
3D-printed buildings, structures and building elements shall be constructed in accordance with this section.
AW104.2 Construction method.
The building construction method, consisting of the manufacturer’s production equipment and fabrication process, shall be in accordance with the UL 3401 report of findings. The unique identifier of the construction method used shall match the identifier in the UL 3401 report of findings.
AW104.3 Additive manufacturing materials.
Only the listed additive manufacturing materials identified in the UL 3401 report of findings shall be used to fabricate the building structure or system components. Containers of the additive manufacturing materials shall be labeled.
AW104.4 Depositing of manufacturing materials.
Manufacturing materials shall only be deposited where ambient temperature and environmental conditions at the job site are within limits specified in the UL 3401 report of findings. The maximum number of layers permitted, specified curing time and any surface preparation or finishing shall be performed as specified in the UL 3401 report of findings.
SECTION AW105
SPECIAL INSPECTIONS
AW105.1 Initial inspection.
An initial inspection of the production equipment, including 3D printer, and the fabrication process shall be performed after the production equipment is located on site and before building fabrication has begun. The inspection shall be conducted by representatives of the approved agency that evaluated the fabrication process for compliance with UL 3401. The inspection shall verify that the fabrication process, including production equipment, 3D-printing parameters and additive manufacturing materials, are in accordance with the UL 3401 report of findings and the proprietary information in the UL 3401 detailed report of findings.
Exception: Where approved by the building official, inspections of the production equipment, including 3D printer, and the fabrication process used in a single housing tract shall be conducted on the first building to be constructed, and on a selected number of subsequent buildings, where the same equipment, equipment operators and fabrication process are used on all buildings. The number of inspections to be performed shall be determined by the building official.